This Project Gantt Chart outlines the Information System Project Management Plan, detailing critical tasks and subtasks necessary for successful project execution. It provides a comprehensive timeline from February to April, covering key areas such as System Initialization, Basic Management, Work Order Management, Customer Management, and Monitoring Reports. Each section specifies the working days required and the start and end dates, ensuring efficient time management and resource allocation. The chart is designed to facilitate project tracking and enhance coordination among team members, ultimately supporting the timely and effective completion of project objectives.
Other creations by the author
Outline/Content
urgent
Information System Project Management Plan - Gantt Chart
NO.
Task
Subtasks
Working hours (days)
Start time
End Time
February
March
April
Week 1
Week 2
Week 3
Week 4
第4周
1
System Initialization
Server Purchase
2
02-01-2023
02-02-2023
System environment deployment
5
02-10-2023
Basic Management
User Management
4
02-11-2023
02-14-2023
Permission Management
02-12-2023
02-17-2023
3
Work Order Management
Create a new work order and query the list
8
02-23-2023
02-28-2023
The work order is completed and feedback is given to the customer
03-03-2023
03-04-2023
Customer Management
15
02-26-2023
03-17-2023
Customer contact management
6
03-18-2023
03-26-2023
Customer contract management
20
03-27-2023
04-24-2023
Monitoring Reports
Employee workload analysis
03-05-2023
03-12-2023
Customer Profile
04-26-2023
04-30-2023